If this plan continues along the proposed timeline, some much needed relief will come online by the middle of October with the other half early to middle next year.
The document is a memo to the NHSA Chairman Richard Wolfe. For more, see the NHSA site: http://www.nhudsonsa.com/ MEMORANDUM
Status of H1 Screening and Wet Weather Pump Station
TO: Richard Wolff/Chairman/North Hudson Sewerage Authority
COPIES: North Hudson Sewerage Authority Board of Commissioners
FROM: Michael Wilson, P.E., Project Manager, CH2M HILL
DATE: August 15, 2011
Chairman Wolff:
As requested, we are providing the monthly update regarding the progress of
construction of the H1 Screening and Wet Weather Pump Station project. This update
is for work that took place during the month of July 2011.
The contractor’s most recent progress schedule is dated August 10, 2011. The progress
schedule reflects continued completion of the few remaining elements of work
associated with the pump station and electric building, as well as continued startup of
new equipment and systems. Significant cleaning and inspection work on the western
pipeline was achieved during the month, and activation of the west pump and western
pipeline is still anticipated for the fall 2011. As noted previously, activation of the
western pump and pipeline is contingent upon timely completion of the pipeline
restoration work. Section C provides a comprehensive schedule narrative and
commentary. The following is a summary of important project issues, milestones
achieved, and the most recent estimate of the project schedule: