Pier C
The contractor is currently working
on site restoration as well as the
evaluation of the site electrical
repairs and landscaping replacements.
The initial sod installed is damaged
the contractor will re-sod with no
additional costs. Graffiti removal
and the decking rehabilitation began
on July 1 and will be followed by
landscaping restoration.
Steven’s Park
Batting Cages – Bid Documents will
be advertised the week of July 8th,
with an anticipated award at the
August 7th regular meeting.
Walkway concrete work started
on 6/28/2013.
Dog Run is currently in design phase.
Church Square Park
Bathroom is in the demolition phase which will be followed by the fit out work including electrical, plumbing and building trades.
Dog Run is currently in design phase.
Church Square Park Concert Series – every Wed on June, July and August from 7 to 9:30pm.
|
Update for Parks
1600 Park
Soft soil conditions were found at
1600 Park. This caused a revision of
the design to strengthen the
foundation for the field lighting.
The lights are critical in accom-
modating the high demand for
field use by all ages in the community.
Completion to is expected for Sept.1
Sinatra Park
Pile driving is complete and sheet
piles have been installed to hold
back the soil. Construction began
for the new pre-cast concrete pier structure which is the foundation
upon which the new soccer field
and walkway will be built.
Completion is expected for Sept.1
Elysian Park
Bids will be received on
7/17/13 with award expected to
be made at the 8/7 Regular
meeting. Construction will commence immediately after
award notification.
Summer Pool Info
The Hoboken High School pool will be open to all residents from July 8 to August 21, Monday through Thursday from 11am to 5pm.
“Mommy and Me” sessions will take place from 3pm to 5pm.
Seacacus Pool available to Hoboken residents at a discounted rate
Click here for more pool info and to download aplications
|